CPWD Analysis of Rates · Flooring
Providing and laying Vitrified tiles in different sizes (thickness to be specified by the manufacturer), with water absorption less than 0.08% and conforming to IS: 15622, of approved brand & manufacturer, in all colours and shade, in skirting, riser of steps, laid with cement based high polymer modified quick set tile adhesive (water based) conforming to IS: 15477, in average 6 mm thickness, including grouting of joints (Payment for grouting of joints to be made separately)
Size of Tile 1000x1000 mm
- Item number
- 11.47.4
- Analysis basis
- Details of cost for 1 sqm
- Priced inputs
- 6
- Derived rate
- ₹2,433.40 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.47.4 — Providing and laying Vitrified tiles in different sizes (thickness to be specified by the manufacturer), with water absorption less than 0.08% and conforming to IS: 15622, of approved brand & manufacturer, in all colours and shade, in skirting, riser of steps, laid with cement based high polymer modified quick set tile adhesive (water based) conforming to IS: 15477, in average 6 mm thickness, including grouting of joints (Payment for grouting of joints to be made separately) Size of Tile 1000x1000 mm — is derived from 6 priced inputs for 1 sqm and works out to ₹2,433.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Vitrified floor tiles 100 x 100 cm size =
- 1.00 sqm+
- 0.025 sqm
- Total = 1.025 sqm
- Add wastage & breakage @ 2.5% =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8623 | Vitrified floor tile 100x100 cmVitrified floor tile 100x100 cm conforming to IS 15622:2006 group (B1a)Material | sqm | 1.025 | 920.00 | 943.00 |
| 9977 | Carriage of tilesMaterial | L.S. | 6.24 | 2.27 | 14.16 |
| 8731 | High polymer modified quickset tile adhesiveMaterial | per kg | 10 | 10.00 | 100.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.25 | 897.00 | 224.25 |
| 0115 | CoolieLabour | day | 0.5 | 736.00 | 368.00 |
| 9988 | Sundries including carriage of quick set polymer etcMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 1,710.50
- Add 1 % Water charges on “W”
- 17.11
- TOTAL
- 1,727.61
- Add GST on “X” (multiplying factor 0.2127)
- 367.46
- TOTAL
- 2,095.07
- Add 15% CPOH on “Y”
- 314.26
- TOTAL
- 2,409.33
- Add Cess @ 1% on “Z”
- 24.09
- Cost for 1 sqm
- 2,433.42
- Say
- 2,433.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 835. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works