CPWD Analysis of Rates · Flooring
Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size
Size of Tile 600 x 600 mm
- Item number
- 11.41A.3.1
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 9
- Derived rate
- ₹1,464.85 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41A.3.1 — Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size Size of Tile 600 x 600 mm — is derived from 9 priced inputs for 10 sqm and works out to ₹1,464.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Glazed Vitrified tiles Matt/Antiskid finish
- 60 x 60 cm size =10 sqm+ Add wastage
- & breakage @2.5% =0.25 sqm. Total =
- 10.25 sqm
- 20 mm thick Cement mortar 1 : 4 (1
- cement : 4 coarse sand)
- Cement for slurry over bed @ 3.3 kg per
- sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2762 | Glazed Vitrified tiles Matt/Antiskid finish of size 60 x 60 cmMaterial | sqm | 10.25 | 486.00 | 4,981.50 |
| 9977 | Carriage of tilesMaterial | L.S. | 62.4 | 2.27 | 141.65 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | Cum | 0.24 | 4,211.70 | 1,010.81 | |
| 9999 | Mortar for pointing in white cementMaterial | L.S. | 26 | 2.27 | 59.02 |
| 0367 | Portland cementPortland Cement (OPC-43 Grade)Material | tonne | 0.033 | 5,156.00 | 170.15 |
| 9999 | For notch trowel,plier, wedge, clips of required thickness, leveling system and rubber mallet etcMaterial | L.S. | 25 | 2.27 | 56.75 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2 | 897.00 | 1,794.00 |
| 0115 | CoolieLabour | day | 2 | 736.00 | 1,472.00 |
| 9988 | sundries including carriage of quick set polymer etcMaterial | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 10,296.74
- Add 1% Water charges on “W”
- 102.97
- TOTAL
- 10,399.71
- Add GST on “X” (multiplying factor 0.2127)
- 2,212.02
- TOTAL
- 12,611.73
- Add 15% CPOH on “Y”
- 1,891.76
- TOTAL
- 14,503.49
- Add Cess @ 1% on “Z”
- 145.03
- Cost of 10 sqm
- 14,648.52
- Cost of 1sqm
- 1,464.85
- Say
- 1,464.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 822. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works