Providing and fixing 1st quality ceramic glazed floor tiles conforming to IS : 15622 (thickness to be specified by the manufacturer ) of approved make in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer-in-Charge in skirting, risers of steps and dados over 12 mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm including pointing in white cement mixed with pigment of matching shade complete

Item number
11.37A
Analysis basis
10 Sqm
Priced inputs
9
Derived rate
₹1,112.70/ SQM
D-01/RATE ANALYSISITEM 11.37A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.37A (Providing and fixing 1st quality ceramic glazed floor tiles conforming to IS : 15622 (thickness to be specified by the manufacturer ) of approved make in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer-in-Charge in skirting, risers of steps and dados over 12 mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm including pointing in white cement mixed with pigment of matching shade complete) is derived from 9 priced inputs for 10 Sqm and works out to ₹1,112.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Add for wastage and breakage @2.5% =
ANALYSIS OF RATES · ITEM 11.37ADETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7801MATGlazed Ceramic Floor Tile = 10 Sqm+Ceramic Glazed Tiles 1st quality 300 x 300 mm in all shades and designs of White, Ivory, grey, Fume Red brown etc.———
OTHER0.25 Sqm =10.25 Sqmsqm10.25200.002,050.00
9999MATCarriage of TilesL.S.62.42.27141.65
SUBCement mortar 1:3 (1 Cement: 3 Coarse Sand)Rate as per item 3.8cum0.144,881.95683.47
9999MATMortar for pointing in white cementL.S.36.42.2782.63
0367MATCement for slurry over bed @3.3 Kg/SqmPortland Cement (OPC-43 Grade)tonne0.0335,156.00170.15
0123LABMason 1st ClassMason 1st classday2.5897.002,242.50
0115LABCoolieday2.5736.001,840.00
9999MATSundries includding carriage of Cement etcL.S.269.12.27610.86
BUILD-UP TO RATE
TOTAL
7,821.26
Add 1 % Water charges on “W”
+78.21
TOTAL
7,899.47
Add GST on “X” (multiplying factor 0.2127)
+1,680.22
TOTAL
9,579.69
Add 15% CPOH on “Y”
+1,436.95
TOTAL
11,016.64
Add Cess @ 1% on “Z”
+110.17
Cost of 10 sqm
11,126.81
Cost of 1 sqm
1,112.68
SAY
₹1,112.70
D-02/SOURCEPRINTED PAGE 809
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
809

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 809. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.