Marble stone flooring with 18 mm thick marble stone, as per sample of marble approved by Engineer-in-charge, over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry, including rubbing and polishing complete with

Udaipur green marble
Item number
11.23.5
Analysis basis
10 sqm
Priced inputs
10
Derived rate
₹2,428.60/ SQM
D-01/RATE ANALYSISITEM 11.23.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.23.5 (Marble stone flooring with 18 mm thick marble stone, as per sample of marble approved by Engineer-in-charge, over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry, including rubbing and polishing complete with : Udaipur green marble) is derived from 10 priced inputs for 10 sqm and works out to ₹2,428.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 20mm thick marble slab = 10.00sqm.+
  • Total = 11.50sqm.
  • Base Cement mortar 1 : 4 (1 cement : 4
  • coarse sand)
  • Cement for slurry @ 4.4kg sqm.
  • (i) for bedding = 44 kg+
  • (ii) for jointing = 6 kg.
  • Total = 50 kg
  • (for finishing, polishing and fixing)
  • Add for wastage 15% = 1.50sqm.
ANALYSIS OF RATES · ITEM 11.23.5DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
6010MATUdaypur green marble slab plain 18mm thickUdaypur green marble slab plain 18 mm thicksqm11.5650.007,475.00
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.2244,211.70943.42
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.055,156.00257.80
9977MATCarriage of marble slabL.S.26.912.2761.09
0123LABMason 1st classMason 1st classday1.2897.001,076.40
0114LABBeldarday1736.00736.00
0115LABCoolieday1736.00736.00
0139LABSkilled Beldar (for floor rubbing etc.)day5816.004,080.00
0013MACHMachine for rubbing of floorsday4350.001,400.00
9988MATSundries and carriage of cement etc.L.S.134.552.27305.43
BUILD-UP TO RATE
TOTAL
17,071.14
Add 1 % Water charges on “W”
+170.71
TOTAL
17,241.85
Add GST on “X” (multiplying factor 0.2127)
+3,667.34
TOTAL
20,909.19
Add 15% CPOH on “Y”
+3,136.38
TOTAL
24,045.57
Add Cess @ 1% on “Z”
+240.46
Cost of 10 sqm.
24,286.03
Cost of 1 sqm.
2,428.60
SAY
₹2,428.60
D-02/SOURCEPRINTED PAGE 796
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
796

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 796. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.