CPWD Analysis of Rates · Flooring

Tile work in skirting, risers of steps and dado up to 2 m height over 12 mm thick bed of cement mortar 1:3 (1 cement :3 coarse sand) and jointed with grey cement slurry @ 3.3 kg/ sqm, including pointing in white cement mixed with pigment of matching shade complete Marble tiles (polished) Raj Nagar

8 mm thick

Item number
11.22.1.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
9
Derived rate
1,475.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.22.1.1 Tile work in skirting, risers of steps and dado up to 2 m height over 12 mm thick bed of cement mortar 1:3 (1 cement :3 coarse sand) and jointed with grey cement slurry @ 3.3 kg/ sqm, including pointing in white cement mixed with pigment of matching shade complete Marble tiles (polished) Raj Nagar 8 mm thick — is derived from 9 priced inputs for 10 sqm and works out to ₹1,475.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • including wastage
  • 12mm thick Cement mortar 1:3 (1 cement : 3 coarse sand)
  • Cement for slurry @ 3.3kg/sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
27518 mm thick marble tiles (polished) Raj NagarMaterialsqm10.61409.004,339.49
9977Carriage of tilesMaterialL.S.392.2788.53
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.144,881.95683.47
9999Mortar for pointing in white cementMaterialL.S.253.52.27575.45
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
9999PigmentMaterialL.S.20.82.2747.22
0123Mason 1st classMason 1st classLabourday2.5897.002,242.50
0115CoolieLabourday2.5736.001,840.00
9988Sundries including carriage of cement etcMaterialL.S.1692.27383.63
TOTAL
10,370.44
Add 1 % Water charges on “W”
103.70
TOTAL
10,474.14
Add GST on “X” (multiplying factor 0.2127)
2,227.85
TOTAL
12,701.99
Add 15% CPOH on “Y”
1,905.30
TOTAL
14,607.29
Add Cess @ 1% on “Z”
146.07
Cost of 10 sqm.
14,753.36
Cost of 1 sqm.
1,475.34
Say
1,475.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 792. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works