Precast terrazo tiles 22 mm thick with graded marble chips of size upto 12 mm, laid in floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement:4 coarse sand)
- Item number
- 11.16.3
- Analysis basis
- 10 sqm
- Priced inputs
- 11
- Derived rate
- ₹1,450.00/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.16.3 (Precast terrazo tiles 22 mm thick with graded marble chips of size upto 12 mm, laid in floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement:4 coarse sand) : Dark shade pigment using ordinary cement) is derived from 11 priced inputs for 10 sqm and works out to ₹1,450.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Ordinary cement for
- (i) Cement slurry @ 4.4kg/sqm = 44kg+
- (ii) Grouting = 44 kg.
- Total = 88kg or 0.088 tonne
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1203 | MAT | Precast terrazo tiles 22 mm thick (dark shade) including 10% wastagePrecast terrazzo tiles 22 mm thick (dark shade) | sqm | 11 | 285.00 | 3,135.00 |
| 9977 | MAT | Carriage of tiles | L.S. | 40.43 | 2.27 | 91.78 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.088 | 5,156.00 | 453.73 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | 3.08 | 75.00 | 231.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.6 | 816.00 | 1,305.60 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 1 | 816.00 | 816.00 |
| 0101 | LAB | Bhisti | day | 1 | 816.00 | 816.00 |
| 0013 | MACH | Machine for rubbing of floors | day | 1.6 | 350.00 | 560.00 |
| 9999 | MAT | Sundries including pigment wherever required and carborandum stone etc | L.S. | 161.98 | 2.27 | 367.69 |
- TOTAL
- 10,192.22
- Add 1 % Water charges on “W”
- +101.92
- TOTAL
- 10,294.14
- Add GST on “X” (multiplying factor 0.2127)
- +2,189.56
- TOTAL
- 12,483.70
- Add 15% CPOH on “Y”
- +1,872.56
- TOTAL
- 14,356.26
- Add Cess @ 1% on “Z”
- +143.56
- Cost of 10 sqm.
- 14,499.82
- Cost of 1 sqm.
- 1,449.98
- SAY
- ₹1,450.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 779
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 779. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.