Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)

Dark shade pigment with ordinary cement
Item number
11.12.1.1
Analysis basis
100 sqm
Priced inputs
11
Derived rate
₹1,864.30/ SQM
D-01/RATE ANALYSISITEM 11.12.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.1 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : Dark shade pigment with ordinary cement) is derived from 11 priced inputs for 100 sqm and works out to ₹1,864.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • For under layer of 12mm thick Cement
  • mortar 1:3 (1 cement : 3 coarse sand)
  • =10x( 0.144 + Extra for rounding 0.03)
  • =0.174x10 = 1.74
  • Top layer 6mm thick
  • @ 3.5kg/50kg of cement
  • =10x40.5x3.5/50=28.4kg
ANALYSIS OF RATES · ITEM 11.12.1.1DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum1.744,881.958,494.59
0785MATMarble chips upto 4mm and downsize White & blackMarble chips up to 4 mm and down size White & blackquintal8.72200.001,744.00
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.4055,156.002,088.18
0784MATMarble dust/ powdercum0.071,180.0082.60
0874MATBlack colour dark shade pigmentkilogram28.475.002,130.00
9977MATCarriage of pigment & marble powder etcL.S.36.42.2782.63
0124LABMason 2nd classMason 2nd classday30816.0024,480.00
0114LABBeldarday30736.0022,080.00
0101LABBhistiday10816.008,160.00
0139LABSkilled Beldar (for floor rubbing etc.)day70816.0057,120.00
9999MATSundriesL.S.2,018.92.274,582.90
BUILD-UP TO RATE
TOTAL
1,31,044.90
Add 1 % Water charges on “W”
+1,310.45
TOTAL
1,32,355.35
Add GST on “X” (multiplying factor 0.2127)
+28,151.98
TOTAL
1,60,507.33
Add 15% CPOH on “Y”
+24,076.10
TOTAL
1,84,583.43
Add Cess @ 1% on “Z”
+1,845.83
Cost of 100 sqm.
1,86,429.26
Cost of 1 sqm.
1,864.29
SAY
₹1,864.30
D-02/SOURCEPRINTED PAGE 772
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
772

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 772. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.