Skip to main content

CPWD Analysis of Rates · Flooring

Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks

1:4 (1 cement : 4 coarse sand)

Item number
11.1.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
7
Derived rate
1,006.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.1.1 Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks: 1:4 (1 cement : 4 coarse sand) — is derived from 7 priced inputs for 10 sqm and works out to ₹1,006.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
2602Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material1000 Nos0.5654,724.002,669.06
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.4344,211.701,827.88
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.025,156.00103.12
0124Mason 2nd classMason 2nd classLabourday1.08816.00881.28
0114BeldarLabourday0.25736.00184.00
0115CoolieLabourday1.62736.001,192.32
0101BhistiLabourday0.27816.00220.32
TOTAL
7,077.98
Add 1 % Water charges on “W”
70.78
TOTAL
7,148.76
Add GST on “X” (multiplying factor 0.2127)
1,520.54
TOTAL
8,669.30
Add 15% CPOH on “Y”
1,300.40
TOTAL
9,969.70
Add Cess @ 1% on “Z”
99.70
Cost of 10 sqm.
10,069.40
Cost of 1 sqm.
1,006.94
Say
1,006.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 755. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.