CPWD Analysis of Rates · Flooring
Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks
1:4 (1 cement : 4 coarse sand)
- Item number
- 11.1.1
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 7
- Derived rate
- ₹1,006.95 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.1.1 — Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks: 1:4 (1 cement : 4 coarse sand) — is derived from 7 priced inputs for 10 sqm and works out to ₹1,006.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material | 1000 Nos | 0.565 | 4,724.00 | 2,669.06 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.434 | 4,211.70 | 1,827.88 | |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.02 | 5,156.00 | 103.12 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.08 | 816.00 | 881.28 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 0115 | CoolieLabour | day | 1.62 | 736.00 | 1,192.32 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
- TOTAL
- 7,077.98
- Add 1 % Water charges on “W”
- 70.78
- TOTAL
- 7,148.76
- Add GST on “X” (multiplying factor 0.2127)
- 1,520.54
- TOTAL
- 8,669.30
- Add 15% CPOH on “Y”
- 1,300.40
- TOTAL
- 9,969.70
- Add Cess @ 1% on “Z”
- 99.70
- Cost of 10 sqm.
- 10,069.40
- Cost of 1 sqm.
- 1,006.94
- Say
- 1,006.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 755. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works