Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks

1:4 (1 cement : 4 coarse sand)
Item number
11.1.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹1,006.95/ SQM
D-01/RATE ANALYSISITEM 11.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.1.1 (Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks: 1:4 (1 cement : 4 coarse sand)) is derived from 7 priced inputs for 10 sqm and works out to ₹1,006.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
ANALYSIS OF RATES · ITEM 11.1.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2602MATCommon burnt clay F.P.S. (non modular) bricks class designation 7.51000 Nos0.5654,724.002,669.06
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.4344,211.701,827.88
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.025,156.00103.12
0124LABMason 2nd classMason 2nd classday1.08816.00881.28
0114LABBeldarday0.25736.00184.00
0115LABCoolieday1.62736.001,192.32
0101LABBhistiday0.27816.00220.32
BUILD-UP TO RATE
TOTAL
7,077.98
Add 1 % Water charges on “W”
+70.78
TOTAL
7,148.76
Add GST on “X” (multiplying factor 0.2127)
+1,520.54
TOTAL
8,669.30
Add 15% CPOH on “Y”
+1,300.40
TOTAL
9,969.70
Add Cess @ 1% on “Z”
+99.70
Cost of 10 sqm.
10,069.40
Cost of 1 sqm.
1,006.94
SAY
₹1,006.95
D-02/SOURCEPRINTED PAGE 755
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
755

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 755. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.