Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks
- Item number
- 11.1.1
- Analysis basis
- 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹1,006.95/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.1.1 (Brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks: 1:4 (1 cement : 4 coarse sand)) is derived from 7 priced inputs for 10 sqm and works out to ₹1,006.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2602 | MAT | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.565 | 4,724.00 | 2,669.06 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.434 | 4,211.70 | 1,827.88 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.02 | 5,156.00 | 103.12 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.08 | 816.00 | 881.28 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0115 | LAB | Coolie | day | 1.62 | 736.00 | 1,192.32 |
| 0101 | LAB | Bhisti | day | 0.27 | 816.00 | 220.32 |
- TOTAL
- 7,077.98
- Add 1 % Water charges on “W”
- +70.78
- TOTAL
- 7,148.76
- Add GST on “X” (multiplying factor 0.2127)
- +1,520.54
- TOTAL
- 8,669.30
- Add 15% CPOH on “Y”
- +1,300.40
- TOTAL
- 9,969.70
- Add Cess @ 1% on “Z”
- +99.70
- Cost of 10 sqm.
- 10,069.40
- Cost of 1 sqm.
- 1,006.94
- SAY
- ₹1,006.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 755
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 755. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.