Painting (one or more coats) on rain water, soil waste and vent pipes and fittings with black anticorrosive bitumastic paint of approved brand and manufacture on old work

75 mm diameter pipes
Item number
13.94.1
Analysis basis
30 metre
Priced inputs
8
Derived rate
₹26.85/ METRE
D-01/RATE ANALYSISITEM 13.94.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.94.1 (Painting (one or more coats) on rain water, soil waste and vent pipes and fittings with black anticorrosive bitumastic paint of approved brand and manufacture on old work : 75 mm diameter pipes) is derived from 8 priced inputs for 30 metre and works out to ₹26.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area=22/7 x0.0814m x30m =7.67 sqm
ANALYSIS OF RATES · ITEM 13.94.1DETAIL OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0828MATAnticorrosive bituminous paint (black)litre0.43120.0051.60
9977MATCarriageL.S.0.392.270.89
0131LABPainterday0.27816.00220.32
0115LABCoolieday0.27736.00198.72
9999MATPutty, sand paper etcL.S.4.162.279.44
9999MATSundriesL.S.6.242.2714.16
9999MATWire brushes for cleaningL.S.4.422.2710.03
9999MATExtra for delaysL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
566.25
Add 1 % Water charges on “W”
+5.66
TOTAL
571.91
Add GST on “X” (multiplying factor 0.2127)
+121.65
TOTAL
693.56
Add 15% CPOH on “Y”
+104.03
TOTAL
797.59
Add Cess @ 1% on “Z”
+7.98
Cost of 30.00 metre
805.57
Cost of 1.00 metre
26.85
SAY
₹26.85
D-02/SOURCEPRINTED PAGE 1018
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1018

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1018. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.