15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix

1:3 (1 cement: 3 fine sand)
Item number
13.8.1
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹494.30/ SQM
D-01/RATE ANALYSISITEM 13.8.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.8.1 (15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix : 1:3 (1 cement: 3 fine sand)) is derived from 9 priced inputs for 10 sqm and works out to ₹494.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 3 (1 cement : 3 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.8.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.1724,379.05753.20
0155LABMason (average)day0.8857.00685.60
0115LABCoolieday0.88736.00647.68
0101LABBhistiday0.99816.00807.84
9999MATScaffolding and sundriesL.S.12.612.2728.62
0367MATPortland Cement (OPC-43 grade)tonne0.025,156.00103.12
0155LABMason (average)day0.27857.00231.39
0115LABCoolieday0.27736.00198.72
9999MATScaffolding and sundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
3,474.47
Add 1 % Water charges on “W”
+34.74
TOTAL
3,509.21
Add GST on “X” (multiplying factor 0.2127)
+746.41
TOTAL
4,255.62
Add 15% CPOH on “Y”
+638.34
TOTAL
4,893.96
Add Cess @ 1% on “Z”
+48.94
Cost of 10.00 sqm
4,942.90
Cost of 1.00 sqm
494.29
SAY
₹494.30
D-02/SOURCEPRINTED PAGE 960
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
960

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 960. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.