12 mm cement plaster finished with a floating coat of neat cement of mix
- Item number
- 13.7.1
- Analysis basis
- 10 sqm
- Priced inputs
- 9
- Derived rate
- ₹439.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.7.1 (12 mm cement plaster finished with a floating coat of neat cement of mix : 1:3 (1 cement: 3 fine sand)) is derived from 9 priced inputs for 10 sqm and works out to ₹439.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.144 | 4,379.05 | 630.58 | |
| 0155 | LAB | Mason (average) | day | 0.67 | 857.00 | 574.19 |
| 0115 | LAB | Coolie | day | 0.75 | 736.00 | 552.00 |
| 0101 | LAB | Bhisti | day | 0.92 | 816.00 | 750.72 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 12.61 | 2.27 | 28.62 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.02 | 5,156.00 | 103.12 |
| 0155 | LAB | Mason (average) | day | 0.27 | 857.00 | 231.39 |
| 0115 | LAB | Coolie | day | 0.27 | 736.00 | 198.72 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 3,087.64
- Add 1 % Water charges on “W”
- +30.88
- TOTAL
- 3,118.52
- Add GST on “X” (multiplying factor 0.2127)
- +663.31
- TOTAL
- 3,781.83
- Add 15% CPOH on “Y”
- +567.27
- TOTAL
- 4,349.10
- Add Cess @ 1% on “Z”
- +43.49
- Cost of 10.00 sqm
- 4,392.59
- Cost of 1.00 sqm
- 439.26
- SAY
- ₹439.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 959
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 959. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.