Skip to main content

CPWD Analysis of Rates · Finishing

Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade

Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture

Item number
13.62.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
13
Derived rate
226.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.62.1 Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture — is derived from 13 priced inputs for 10 sqm and works out to ₹226.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0806Ready mixed pink or grey primer on wood work (hard and soft wood) having VOC content less than 50 grams/ litreMateriallitre0.75100.0075.00
9999PuttyMaterialL.S.2.732.276.20
9977CarriageMaterialL.S.0.392.270.89
0131PainterLabourday0.25816.00204.00
0115CoolieLabourday0.25736.00184.00
9999Brushes, sand paper etcMaterialL.S.5.332.2712.10
9999SundriesMaterialL.S.10.792.2724.49
0833Synthetic enamel paint in black or chocolate shadeMateriallitre1.16180.00208.80
9977Carriage of paint and materialMaterialL.S.1.432.273.25
0131PainterLabourday0.54816.00440.64
0115CoolieLabourday0.54736.00397.44
9999Brushes, sand paper etcMaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.8.062.2718.30
TOTAL
1,590.46
Add 1 % Water charges on “W”
15.90
TOTAL
1,606.36
Add GST on “X” (multiplying factor 0.2127)
341.67
TOTAL
1,948.03
Add 15% CPOH on “Y”
292.20
TOTAL
2,240.23
Add Cess @ 1% on “Z”
22.40
Cost of 10.00 sqm
2,262.63
Cost of 1.00 sqm
226.26
Say
226.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1000. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works