Painting (two or more coats) on rain water, soil waste and vent pipes and fittings with synthetic enamel paint of approved brand and manufacture and required colour over a priming coat of approved steel primer on new work

150 mm diameter pipes

Item number
13.56.2
Analysis basis
Detail of cost for 30 metre
Priced inputs
13
Derived rate
122.15 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.56.2 Painting (two or more coats) on rain water, soil waste and vent pipes and fittings with synthetic enamel paint of approved brand and manufacture and required colour over a priming coat of approved steel primer on new work 150 mm diameter pipes — is derived from 13 priced inputs for 30 metre and works out to ₹122.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Area=22/7 x157.2mm x30m =14.82sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
4202Red oxide Zinc chromate primerMateriallitre0.8140.00112.00
9977CarriageMaterialL.S.0.652.271.48
0131PainterLabourday0.36816.00293.76
0115CoolieLabourday0.36736.00264.96
9999SundriesMaterialL.S.15.992.2736.30
0833Synthetic enamel paint in black or chocolate shadeMateriallitre1.72180.00309.60
9977CarriageMaterialL.S.2.082.274.72
9999Putty, sand paper etcMaterialL.S.7.932.2718.00
0131PainterLabourday0.8816.00652.80
0115CoolieLabourday0.8736.00588.80
9999SundriesMaterialL.S.10.012.2722.72
9999Wire brushes for cleaningMaterialL.S.17.812.2740.43
9999Extra for delaysMaterialL.S.101.42.27230.18
TOTAL
2,575.75
Add 1 % Water charges on “W”
25.76
TOTAL
2,601.51
Add GST on “X” (multiplying factor 0.2127)
553.34
TOTAL
3,154.85
Add 15% CPOH on “Y”
473.23
TOTAL
3,628.08
Add Cess @ 1% on “Z”
36.28
Cost of 30.00 metre
3,664.36
Cost of 1.00 metre
122.15
Say
122.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 997. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.