15 mm cement plaster on rough side of single or half brick wall of mix
- Item number
- 13.5.2
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹395.35/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.5.2 (15 mm cement plaster on rough side of single or half brick wall of mix: 1:6 (1 cement: 6 coarse sand)) is derived from 5 priced inputs for 10 sqm and works out to ₹395.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 6 (1 cement : 6 coarse
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11 | cum | 0.172 | 3,541.40 | 609.12 | |
| 0155 | LAB | Mason (average) | day | 0.8 | 857.00 | 685.60 |
| 0115 | LAB | Coolie | day | 0.88 | 736.00 | 647.68 |
| 0101 | LAB | Bhisti | day | 0.99 | 816.00 | 807.84 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 12.61 | 2.27 | 28.62 |
- TOTAL
- 2,778.86
- Add 1 % Water charges on “W”
- +27.79
- TOTAL
- 2,806.65
- Add GST on “X” (multiplying factor 0.2127)
- +596.97
- TOTAL
- 3,403.62
- Add 15% CPOH on “Y”
- +510.54
- TOTAL
- 3,914.16
- Add Cess @ 1% on “Z”
- +39.14
- Cost of 10.00 sqm
- 3,953.30
- Cost of 1.00 sqm
- 395.33
- SAY
- ₹395.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 957
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 957. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.