Skip to main content
R/DAR 2023

Colour washing such as green, blue or buff to give an even shade

New work (two or more coats) with a base coat of white washing with lime
Item number
13.39.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹53.30/ SQM
D-01/RATE ANALYSISITEM 13.39.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.39.1 (Colour washing such as green, blue or buff to give an even shade : New work (two or more coats) with a base coat of white washing with lime) is derived from 7 priced inputs for 10 sqm and works out to ₹53.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.39.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0775MATDehradun white limequintal0.03650.0019.50
9977MATCarriage of limeL.S.8.062.2718.30
9999MATAdd for colouring stuffL.S.0.912.272.07
0141LABWhite Washerday0.3816.00244.80
0115LABCoolieday0.1736.0073.60
9999MATIndigo gum etcL.S.4.422.2710.03
9999MATSundries ladders etcL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
374.50
Add 1 % Water charges on “W”
+3.75
TOTAL
378.25
Add GST on “X” (multiplying factor 0.2127)
+80.45
TOTAL
458.70
Add 15% CPOH on “Y”
+68.81
TOTAL
527.51
Add Cess @ 1% on “Z”
+5.28
Cost of 10.00 sqm
532.79
Cost of 1.00 sqm
53.28
SAY
₹53.30
D-02/SOURCEPRINTED PAGE 984
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
984

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 984. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.