Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand)
- Item number
- 13.33.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹385.40/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.33.1 (Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) : Flush/ Ruled pointing) is derived from 6 priced inputs for 10 sqm and works out to ₹385.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.023 | 4,379.05 | 100.72 | |
| 9999 | MAT | Sundries | L.S. | 7.15 | 2.27 | 16.23 |
| 0155 | LAB | Mason (average) | day | 0.92 | 857.00 | 788.44 |
| 0115 | LAB | Coolie | day | 1.37 | 736.00 | 1,008.32 |
| 0101 | LAB | Bhisti | day | 0.93 | 816.00 | 758.88 |
| 9999 | MAT | Scaffolding and racking out joints including sundries | L.S. | 16.12 | 2.27 | 36.59 |
- TOTAL
- 2,709.18
- Add 1 % Water charges on “W”
- +27.09
- TOTAL
- 2,736.27
- Add GST on “X” (multiplying factor 0.2127)
- +582.00
- TOTAL
- 3,318.27
- Add 15% CPOH on “Y”
- +497.74
- TOTAL
- 3,816.01
- Add Cess @ 1% on “Z”
- +38.16
- Cost of 10.00 sqm
- 3,854.17
- Cost of 1.00 sqm
- 385.42
- SAY
- ₹385.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 980
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 980. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.