Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete

Item number
13.26
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹262.70/ SQM
D-01/RATE ANALYSISITEM 13.26

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.26 (Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete) is derived from 5 priced inputs for 10 sqm and works out to ₹262.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Plaster of paris 10x0.002x1121 = 22.42kg
  • Total = 22.87kg. Say23kg
  • Add 2% wastage= 0.45kg
ANALYSIS OF RATES · ITEM 13.26DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0869MATPlaster of Pariskilogram237.00161.00
9977MATCarriage of plaster of parisL.S.3.92.278.85
0122LABMason (for plaster of paris work) 1st classday0.91897.00816.27
0114LABBeldarday0.91736.00669.76
9999MATScaffolding and sundriesL.S.83.982.27190.63
BUILD-UP TO RATE
TOTAL
1,846.51
Add 1 % Water charges on “W”
+18.47
TOTAL
1,864.98
Add GST on “X” (multiplying factor 0.2127)
+396.68
TOTAL
2,261.66
Add 15% CPOH on “Y”
+339.25
TOTAL
2,600.91
Add Cess @ 1% on “Z”
+26.01
Cost of 10.00 sqm
2,626.92
Cost of 1.00 sqm
262.69
SAY
₹262.70
D-02/SOURCEPRINTED PAGE 973
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
973

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 973. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.