Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete
- Item number
- 13.26
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹262.70/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.26 (Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete) is derived from 5 priced inputs for 10 sqm and works out to ₹262.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Plaster of paris 10x0.002x1121 = 22.42kg
- Total = 22.87kg. Say23kg
- Add 2% wastage= 0.45kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0869 | MAT | Plaster of Paris | kilogram | 23 | 7.00 | 161.00 |
| 9977 | MAT | Carriage of plaster of paris | L.S. | 3.9 | 2.27 | 8.85 |
| 0122 | LAB | Mason (for plaster of paris work) 1st class | day | 0.91 | 897.00 | 816.27 |
| 0114 | LAB | Beldar | day | 0.91 | 736.00 | 669.76 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 83.98 | 2.27 | 190.63 |
- TOTAL
- 1,846.51
- Add 1 % Water charges on “W”
- +18.47
- TOTAL
- 1,864.98
- Add GST on “X” (multiplying factor 0.2127)
- +396.68
- TOTAL
- 2,261.66
- Add 15% CPOH on “Y”
- +339.25
- TOTAL
- 2,600.91
- Add Cess @ 1% on “Z”
- +26.01
- Cost of 10.00 sqm
- 2,626.92
- Cost of 1.00 sqm
- 262.69
- SAY
- ₹262.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 973
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 973. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.