15 mm cement plaster on the rough side of single or half brick wall of mix

1:4 (1 cement: 4 fine sand)
Item number
13.2.1
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹399.45/ SQM
D-01/RATE ANALYSISITEM 13.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.2.1 (15 mm cement plaster on the rough side of single or half brick wall of mix : 1:4 (1 cement: 4 fine sand)) is derived from 5 priced inputs for 10 sqm and works out to ₹399.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.2.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.4 of SH: MortarsRate as per item 3.4cum0.1723,708.80637.91
0155LABMason (average)day0.8857.00685.60
0115LABCoolieday0.88736.00647.68
0101LABBhistiday0.99816.00807.84
9999MATScaffolding and sundriesL.S.12.612.2728.62
BUILD-UP TO RATE
TOTAL
2,807.65
Add 1 % Water charges on “W”
+28.08
TOTAL
2,835.73
Add GST on “X” (multiplying factor 0.2127)
+603.16
TOTAL
3,438.89
Add 15% CPOH on “Y”
+515.83
TOTAL
3,954.72
Add Cess @ 1% on “Z”
+39.55
Cost of 10.00 sqm
3,994.27
Cost of 1.00 sqm
399.43
SAY
₹399.45
D-02/SOURCEPRINTED PAGE 954
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
954

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 954. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.