Skip to main content
R/DAR 2023

15 mm cement plaster 1:2 (1 cement : 2 stone dust) on the rough side of single or half brick wall

Item number
13.14
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹437.20/ SQM
D-01/RATE ANALYSISITEM 13.14

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.14 (15 mm cement plaster 1:2 (1 cement : 2 stone dust) on the rough side of single or half brick wall) is derived from 5 priced inputs for 10 sqm and works out to ₹437.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:2 (1 Cement : 2 stone
  • dust)
ANALYSIS OF RATES · ITEM 13.14DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.12 of SH: MortarsRate as per item 3.12cum0.1725,252.00903.34
0155LABMason (average)day0.8857.00685.60
0115LABCoolieday0.88736.00647.68
0101LABBhistiday0.99816.00807.84
9999MATScaffolding and sundriesL.S.12.612.2728.62
BUILD-UP TO RATE
TOTAL
3,073.08
Add 1 % Water charges on “W”
+30.73
TOTAL
3,103.81
Add GST on “X” (multiplying factor 0.2127)
+660.18
TOTAL
3,763.99
Add 15% CPOH on “Y”
+564.60
TOTAL
4,328.59
Add Cess @ 1% on “Z”
+43.29
Cost of 10.00 sqm
4,371.88
Cost of 1.00 sqm
437.19
SAY
₹437.20
D-02/SOURCEPRINTED PAGE 964
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
964

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 964. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.