CPWD Analysis of Rates · Earth Work

Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m

Ordinary rock

Item number
2.9.1
Analysis basis
Details of cost for 100 cum.
Priced inputs
8
Derived rate
632.95 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.9.1 Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m Ordinary rock — is derived from 8 priced inputs for 100 cum and works out to ₹632.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0020Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachineryday0.6257,850.004,906.25
0017Hire and running charges of tipperMachineryday0.6254,200.002,625.00
0132Rock ExcavatorLabourday8.85736.006,513.60
0133Rock BreakerLabourday17.65736.0012,990.40
0134Rock Hole DrillerLabourday5.3736.003,900.80
0114BeldarLabourday5736.003,680.00
0115CoolieLabourday13736.009,568.00
9999SundriesMaterialL.S.135.22.27306.90
TOTAL
44,490.95
Add 1 % Water charges on “W”
444.91
TOTAL
44,935.86
Add GST on “X” (multiplying factor 0.2127)
9,557.86
TOTAL
54,493.72
Add 15% CPOH on “Y”
8,174.06
TOTAL
62,667.78
Add Cess @ 1% on “Z”
626.68
Cost of 100 cum.
63,294.46
Cost of 1 cum.
632.94
Say
632.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 98. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.