Skip to main content
R/DAR 2023

Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m

Ordinary rock
Item number
2.9.1
Analysis basis
100 cum
Priced inputs
8
Derived rate
₹632.95/ CUM
D-01/RATE ANALYSISITEM 2.9.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.9.1 (Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m Ordinary rock) is derived from 8 priced inputs for 100 cum and works out to ₹632.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.9.1DETAILS OF COST FOR 100 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0020MACHHydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelday0.6257,850.004,906.25
0017MACHHire and running charges of tipperday0.6254,200.002,625.00
0132LABRock Excavatorday8.85736.006,513.60
0133LABRock Breakerday17.65736.0012,990.40
0134LABRock Hole Drillerday5.3736.003,900.80
0114LABBeldarday5736.003,680.00
0115LABCoolieday13736.009,568.00
9999MATSundriesL.S.135.22.27306.90
BUILD-UP TO RATE
TOTAL
44,490.95
Add 1 % Water charges on “W”
+444.91
TOTAL
44,935.86
Add GST on “X” (multiplying factor 0.2127)
+9,557.86
TOTAL
54,493.72
Add 15% CPOH on “Y”
+8,174.06
TOTAL
62,667.78
Add Cess @ 1% on “Z”
+626.68
Cost of 100 cum.
63,294.46
Cost of 1 cum.
632.94
SAY
₹632.95
D-02/SOURCEPRINTED PAGE 98
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
98

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 98. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.