Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
- Item number
- 2.31
- Analysis basis
- 100 sqm
- Priced inputs
- 2
- Derived rate
- ₹17.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.31 (Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared) is derived from 2 priced inputs for 100 sqm and works out to ₹17.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 1.08 | 736.00 | 794.88 |
| 0115 | LAB | Coolie | day | 0.6 | 736.00 | 441.60 |
- TOTAL
- 1,236.48
- Add 1 % Water charges on “W”
- +12.36
- TOTAL
- 1,248.84
- Add GST on “X” (multiplying factor 0.2127)
- +265.63
- TOTAL
- 1,514.47
- Add 15% CPOH on “Y”
- +227.17
- TOTAL
- 1,741.64
- Add Cess @ 1% on “Z”
- +17.42
- Cost of 100 sqm.
- 1,759.06
- Cost of 1 sqm.
- 17.59
- SAY
- ₹17.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 132
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 132. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.