Close timbering over areas including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered)

Depth not exceeding 1.5 m
Item number
2.18.1
Analysis basis
10 area
Priced inputs
6
Derived rate
₹125.80/ AREA
D-01/RATE ANALYSISITEM 2.18.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.18.1 (Close timbering over areas including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered): Depth not exceeding 1.5 m) is derived from 6 priced inputs for 10 area and works out to ₹125.80 per area after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.50m deepArea -10x30x1.5m = 450 sqm.
  • The Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Poling boards of
  • Size 250x38mm = 450x0.038 = 17.1 cum =
  • 17100 cudm
  • Qty taken for cost of using once after
  • deducting for credit = 17100x x = 1068.75
  • dm
  • Wallings l00mmx 100mm of ¼ ¼
  • 100x100mm : 10x30x0.10x0.10 = 3 cum =
  • 3000 cudm
  • Qty taken for cost of using once after
  • deducting for credit = 3000x x = 187.5
  • dm
  • Raking struts ¼ ¼
  • 10x17 x 1.5 = 255m
  • Qty taken for cost of using once after
  • deducting for credit = 255x x = 15.9 m
ANALYSIS OF RATES · ITEM 2.18.1DETAILS OF COST FOR 10 AREA 30M LONG AND
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in planks10 cudm106.875260.0027,787.50
1197MATSecond ³ class kail wood in scantlingSecond class kail wood in scantling10 cudm18.75260.004,875.00
0302MATSafeda ³ ballies 125 mm diameterSafeda ballies 125 mm diametermetre15.944.00699.60
0112LABCarpenter 2nd classday2.5816.002,040.00
0114LABBeldar ¼ ¼Beldarday5736.003,680.00
9999MATSundriesL.S.314.62.27714.14
BUILD-UP TO RATE
TOTAL
39,796.24
Add 1 % Water charges on “W”
+397.96
TOTAL
40,194.20
Add GST on “X” (multiplying factor 0.2127)
+8,549.31
TOTAL
48,743.51
Add 15% CPOH on “Y”
+7,311.53
TOTAL
56,055.04
Add Cess @ 1% on “Z”
+560.55
Cost of 450 Sqm.
56,615.59
Cost per sqm.
125.81
SAY
₹125.80
D-02/SOURCEPRINTED PAGE 115
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
115

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 115. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.