Skip to main content

CPWD Analysis of Rates · Earth Work

Close timbering over areas including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered)

Depth not exceeding 1.5 m

Item number
2.18.1
Analysis basis
Details of cost for 10 area 30m long and
Priced inputs
6
Derived rate
125.80 / area

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.18.1 Close timbering over areas including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered): Depth not exceeding 1.5 m — is derived from 6 priced inputs for 10 area and works out to ₹125.80 per area after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.50m deepArea -10x30x1.5m = 450 sqm.
  • The Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Poling boards of
  • Size 250x38mm = 450x0.038 = 17.1 cum =
  • 17100 cudm
  • Qty taken for cost of using once after
  • deducting for credit = 17100x x = 1068.75
  • dm
  • Wallings l00mmx 100mm of ¼ ¼
  • 100x100mm : 10x30x0.10x0.10 = 3 cum =
  • 3000 cudm
  • Qty taken for cost of using once after
  • deducting for credit = 3000x x = 187.5
  • dm
  • Raking struts ¼ ¼
  • 10x17 x 1.5 = 255m
  • Qty taken for cost of using once after
  • deducting for credit = 255x x = 15.9 m
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterial10 cudm106.875260.0027,787.50
1197Second ³ class kail wood in scantlingSecond class kail wood in scantlingMaterial10 cudm18.75260.004,875.00
0302Safeda ³ ballies 125 mm diameterSafeda ballies 125 mm diameterMaterialmetre15.944.00699.60
0112Carpenter 2nd classLabourday2.5816.002,040.00
0114Beldar ¼ ¼BeldarLabourday5736.003,680.00
9999SundriesMaterialL.S.314.62.27714.14
TOTAL
39,796.24
Add 1 % Water charges on “W”
397.96
TOTAL
40,194.20
Add GST on “X” (multiplying factor 0.2127)
8,549.31
TOTAL
48,743.51
Add 15% CPOH on “Y”
7,311.53
TOTAL
56,055.04
Add Cess @ 1% on “Z”
560.55
Cost of 450 Sqm.
56,615.59
Cost per sqm.
125.81
Say
125.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 115. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works