R/DAR 2023

Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg)

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Item number
19.7.2.1
Analysis basis
1 manhole
Priced inputs
13
Derived rate
₹26,405.50/ MANHOLE
D-01/RATE ANALYSISITEM 19.7.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.7.2.1 (Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg) : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 13 priced inputs for 1 manhole and works out to ₹26,405.50 per manhole after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:4:8 (1 cement : 4
  • coarse sand : 8 graded stone aggregate
  • 40 mm nominal size)
  • 1.81x1.51x0.20 m = 0.547 cum Say 0.55
  • cum
  • Brick work with bricks of class designation 7.5 in foundation & plinth in cement
  • mortar 1:4 (1 cement : 4 coarse sand)
  • 5.12x0.23x0.80 m = 0.942 cum
  • =(-) 0.008 cum
  • Total= 0.934 cum Say 0.93 cum
  • Cement concrete 1:2:4 (1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size) for benching
  • 2x1.20x(0.90/2) x (0.30+0.20)/2 = 2.70
  • cum
  • 0.021 cum
  • Total= 0.249 cum say 0.25
  • 12 mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • 4.20mx0.50m = 2.10 sqm
  • 2x½x0.90x0.10m = 0.09 sqm
  • = 2.19 sqm
  • Reinforced cement concrete 1:1.5:3 (1
  • cement : 1.5 coarse sand : 3 graded
  • stone aggregate 20 mm nominal size)
  • For slab : 1.66x1.36x0.15m = 0.339 cum
  • (-) 0.029 cum
  • = 0.31 cum
  • T.M.T. bars steel reinforcement for R.C.C
  • work of slab
  • 0.31 cum @ 80.09 kg/cum = 24.83 kg
  • Form work = 1.20x0.90 = 1.08 sqm
  • sqm
  • = 0.884 sqm Say 0.88 sqm
  • Extra labour for making channel :
  • Less for pipe 2x3.14x(0.15m)²x0.23m
  • Less for pipe 1.20x3.14/4x(0.15m)² = (-)
  • Less for cover 0.7854x(0.50)²x0.15m =
  • Less cover = 3.14/4x(0.50)² = (-) 0.196
ANALYSIS OF RATES · ITEM 19.7.2.1DETAILS OF COST FOR 1 MANHOLE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.8 of SH : Concrete WorkRate as per item 4.1.8cum0.556,812.003,746.60
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.937,370.656,854.70
SUBRate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.257,878.501,969.63
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm2.19449.55984.51
SUBRate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2cum0.319,045.752,804.18
SUBRate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6kg24.83107.852,677.92
SUBRate as per item no 5.9.3 of SH : RCC WorkRate as per item 5.9.3sqm0.88927.25815.98
0123LABMason 1st classMason 1st classday0.08897.0071.76
0124LABMason 2nd classMason 2nd classday0.08816.0065.28
1356MAT500 mm dia cover with frame (medium duty)C.I. 500 mm dia cover with frame (medium duty)each14,400.004,400.00
9977MATCarriage of C.I. cover & frameL.S.6.762.2715.35
9999MATPainting of C.I. cover & frame with coal tarL.S.6.762.2715.35
9999MATSundriesL.S.16.642.2737.77
BUILD-UP TO RATE
TOTAL
24,459.03
Add 1 % Water charges on “W-A”
+46.06
TOTAL
24,505.09
Add GST on “X-A” (multiplying factor 0.2127)
+989.39
TOTAL
25,494.48
Add 15% CPOH on “Y-A”
+846.14
TOTAL
26,340.62
Add Cess @ 1% on “Z-A”
+64.87
Cost of each
26,405.49
SAY
₹26,405.50
D-02/SOURCEPRINTED PAGE 1718
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1718

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1718. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.