Extra for depth beyond 45 cm of brick masonry chamber : For 500x700 mm size
- Item number
- 19.31.2.1
- Analysis basis
- one metre
- Priced inputs
- 2
- Derived rate
- ₹6,680.60/ ONE METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.31.2.1 (Extra for depth beyond 45 cm of brick masonry chamber : For 500x700 mm size With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 2 priced inputs for one metre and works out to ₹6,680.60 per one metre after water charges, GST, CPOH and cess. The full build-up is below.
- Brick work in bricks of class designation
- 7.5 in cement mortar 1:4 ( 1 cement : 4
- fine sand)
- 3.32 m x 0.23m x1.00 m = 0.76 cum
- 12 mm cement plaster 1:3 (1 cement : 3
- coarse sand finished with floating coat of
- neat cement
- Wall : 2.40x1.00 m = 2.40 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1 | cum | 0.76 | 7,370.65 | 5,601.69 | |
| SUB | Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1 | sqm | 2.4 | 449.55 | 1,078.92 |
- TOTAL
- 6,680.61
- Cost per metre
- 6,680.61
- SAY
- ₹6,680.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1773
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1773. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.