Skip to main content
R/DAR 2023

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design

200 mm diameter S.W. pipe
Item number
19.2.3
Analysis basis
10 metre
Priced inputs
1
Derived rate
₹1,375.45/ METRE
D-01/RATE ANALYSISITEM 19.2.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.2.3 (Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design : 200 mm diameter S.W. pipe) is derived from 1 priced inputs for 10 metre and works out to ₹1,375.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area = W x W/2 + ½ x (3.14 x W² / 4)(3.14 x D² / 4)
  • = W² x (0.5 + 3.14 / 8) - (3.14 x D² / 4)
  • Where W = D + X
  • D = 200 + 17 + 17 = 234 mm or 23.4 cm
  • X = 300 mm as trench depth is less than
  • 1200 mm
  • W = 23.4 + 30 = 53.4
  • Area = 53.4² x ( 0.5 + 3.14 / 8) - (3.14 x
  • 23.4²/4)
  • = 2115 sqcm = 0.2115 sqm Say 0.211
  • sqm
  • For 10 m length qty. of concrete reqd. =
  • 2.11 cum
ANALYSIS OF RATES · ITEM 19.2.3DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10cum2.116,518.6013,754.25
BUILD-UP TO RATE
Cost of 10 metre
13,754.25
Cost of metre
1,375.43
SAY
₹1,375.45
D-02/SOURCEPRINTED PAGE 1694
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1694

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1694. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.