Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design
- Item number
- 19.15.1
- Analysis basis
- one M
- Priced inputs
- 8
- Derived rate
- ₹544.70/ ONE M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.15.1 (Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design : With 20x20 mm square bar) is derived from 8 priced inputs for one M and works out to ₹544.70 per one m after water charges, GST, CPOH and cess. The full build-up is below.
- M.S. 20 mm square bar 0.75 m @ 3.137
- kg/m = 0.024
- LABOUR for fabrication
- Cement concrete 1:3:6 (1 cement : 3
- coarse sand : 6 graded stone aggregate
- : 20 mm nominal size)
- 0.20x0.20x0.10 m = 0.004 cum
- LABOUR for fixing M.S. foot rests
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1006 | MAT | Mild steel square bars | quintal | 0.024 | 5,500.00 | 132.00 |
| 9988 | MAT | Carriage, painting, and other sundries | L.S. | 1.82 | 2.27 | 4.13 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.1 | 816.00 | 81.60 |
| 0114 | LAB | Beldar | day | 0.1 | 736.00 | 73.60 |
| SUB | Rate as per item no 4.1.5 of SH : Concrete workRate as per item 4.1.5 | cum | 0.004 | 7,294.70 | 29.18 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.02 | 897.00 | 17.94 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.02 | 816.00 | 16.32 |
| 0114 | LAB | Beldar | day | 0.05 | 736.00 | 36.80 |
- TOTAL
- 391.57
- Add 1 % Water charges on “W-A”
- +3.62
- TOTAL
- 395.19
- Add GST on “X-A” (multiplying factor 0.2127)
- +77.85
- TOTAL
- 473.04
- Add 15% CPOH on “Y-A”
- +66.58
- TOTAL
- 539.62
- Add Cess @ 1% on “Z-A”
- +5.10
- Cost for 1 no.
- 544.72
- SAY
- ₹544.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1739
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1739. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.