CPWD Analysis of Rates · Drainage

Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design

With 20x20 mm square bar

Item number
19.15.1
Analysis basis
Details of cost for one M.S foot rests
Priced inputs
8
Derived rate
544.70 / one M

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.15.1 Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design : With 20x20 mm square bar — is derived from 8 priced inputs for one M and works out to ₹544.70 per one m after water charges, GST, CPOH and cess. The full build-up is below.

  • M.S. 20 mm square bar 0.75 m @ 3.137
  • kg/m = 0.024
  • LABOUR for fabrication
  • Cement concrete 1:3:6 (1 cement : 3
  • coarse sand : 6 graded stone aggregate
  • : 20 mm nominal size)
  • 0.20x0.20x0.10 m = 0.004 cum
  • LABOUR for fixing M.S. foot rests
CodeInputUnitQuantityRate (INR)Amount (INR)
1006Mild steel square barsMaterialquintal0.0245,500.00132.00
9988Carriage, painting, and other sundriesMaterialL.S.1.822.274.13
0103Blacksmith 2nd classLabourday0.1816.0081.60
0114BeldarLabourday0.1736.0073.60
Rate as per item no 4.1.5 of SH : Concrete workRate as per item 4.1.5Sub-analysiscum0.0047,294.7029.18
0123Mason 1st classMason 1st classLabourday0.02897.0017.94
0124Mason 2nd classMason 2nd classLabourday0.02816.0016.32
0114BeldarLabourday0.05736.0036.80
TOTAL
391.57
Add 1 % Water charges on “W-A”
3.62
TOTAL
395.19
Add GST on “X-A” (multiplying factor 0.2127)
77.85
TOTAL
473.04
Add 15% CPOH on “Y-A”
66.58
TOTAL
539.62
Add Cess @ 1% on “Z-A”
5.10
Cost for 1 no.
544.72
Say
544.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1739. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.