Extra depth for circular type manhole 1.22 m internal dia (at bottom) beyond 1.68 m to 2.29 m

With Sewer bricks conforming IS : 4885
Item number
19.12.2
Analysis basis
Detail of cost of 0.61 m extra depth
Priced inputs
2
Derived rate
₹9,674.40
D-01/RATE ANALYSISITEM 19.12.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.12.2 (Extra depth for circular type manhole 1.22 m internal dia (at bottom) beyond 1.68 m to 2.29 m : With Sewer bricks conforming IS : 4885) is derived from 2 priced inputs and works out to ₹9,674.40 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Brick work with modular extruded brunt
  • fly ash clay sewer bricks (Conforming
  • to IS: 4885 ) in cement mortar 1:4 (1
  • cement : 4 coarse sand)
  • 12mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement.
ANALYSIS OF RATES · ITEM 19.12.2DETAIL OF COST OF 0.61 M EXTRA DEPTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No 6.36.1 of SH : Brick WorkRate as per item 6.36.1cum0.667,197.754,750.52
SUBRate as per item no 13.9.1 of SH : ] FinishingRate as per item 13.9.1sqm2.56449.551,150.85
BUILD-UP TO RATE
Cost for 0.61 metre
5,901.37
Cost for 1.00 metre
9,674.38
SAY
₹9,674.40
D-02/SOURCEPRINTED PAGE 1734
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1734

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1734. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.