Skip to main content
R/DAR 2023

Extra depth for circular type manhole 0.91m internal dia (at bottom) beyond 0.91 m to 1.67 m

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Item number
19.10.1
Analysis basis
Detail of cost of 0.76 m depth
Priced inputs
3
Derived rate
₹7,591.80
D-01/RATE ANALYSISITEM 19.10.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.10.1 (Extra depth for circular type manhole 0.91m internal dia (at bottom) beyond 0.91 m to 1.67 m With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 3 priced inputs and works out to ₹7,591.80 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Brick work in foundation with 7.5 class
  • designation bricks in cement mortar 1:4
  • (1 cement : 4 coarse sand)
  • Cement concrete 1:2:4 (1 cement : 2
  • coarse sand : 4 graded stone 20mm
  • nominal size)
  • 12mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with neat cement.
ANALYSIS OF RATES · ITEM 19.10.1DETAIL OF COST OF 0.76 M DEPTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.637,370.654,643.51
SUBRate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.017,878.5078.79
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm2.33449.551,047.45
BUILD-UP TO RATE
Cost for 0.76 metre
5,769.75
Cost for 1.00 metre
7,591.78
SAY
₹7,591.80
D-02/SOURCEPRINTED PAGE 1729
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1729

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1729. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.