Skip to main content

Applying breathable, non-reactive, antifungal, and water repellant Silane/Siloxane chemical as approved by Archaeological Survey of India/ Engineer-in-charge, of approved brand and manufacture, diluted with solvent mineral Turpentine oil in the ratio of 1:12 (One part of approved chemical :12 Part of Turpentine oil), on the existing sand stone masonry surface with two or more coats to give uniform application of chemical on the surface, all complete as per direction of Engineer-In-charge (The rate is inclusive of all materials & labours involved except scaffolding)

Item number
24.8
Analysis basis
45 sqm
Priced inputs
5
Derived rate
₹109.90/ SQM
D-01/RATE ANALYSISITEM 24.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 24.8 (Applying breathable, non-reactive, antifungal, and water repellant Silane/Siloxane chemical as approved by Archaeological Survey of India/ Engineer-in-charge, of approved brand and manufacture, diluted with solvent mineral Turpentine oil in the ratio of 1:12 (One part of approved chemical :12 Part of Turpentine oil), on the existing sand stone masonry surface with two or more coats to give uniform application of chemical on the surface, all complete as per direction of Engineer-In-charge (The rate is inclusive of all materials & labours involved except scaffolding)) is derived from 5 priced inputs for 45 sqm and works out to ₹109.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 24.8DETAIL OF COST FOR 45 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7768MATWater repallent chemical approved by ASIlitre11,190.001,190.00
7770MATTurpentine oillitre1260.00720.00
0131LABPainterday1816.00816.00
0114LABBeldarday1736.00736.00
9999MATHandling / Transportation chargesL.S.62.2713.62
BUILD-UP TO RATE
TOTAL
3,475.62
Add 1 % Water charges on “W”
+34.76
TOTAL
3,510.38
Add GST on “X” (multiplying factor 0.2127)
+746.66
TOTAL
4,257.04
Add 15% CPOH on “Y”
+638.56
TOTAL
4,895.60
Add Cess @ 1% on “Z”
+48.96
Cost of 45.00 sqm
4,944.56
Cost of 1.00 sqm
109.88
SAY
₹109.90
D-02/SOURCEPRINTED PAGE 1894
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1894

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1894. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONSERVATION OF HERITAGE BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.