Ruled/ Flush pointing on White sand stone masonry surface with lime, surkhi and marble dust mortar in the ratio of 1:1.5:1/2 {One lime : 1.5 surkhi (15% dark red and 85% light yellow surkhi) : 1/2 marble dust}. (The rate is inclusive of all materials & labours involved except scaffolding)

Item number
24.6
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹374.30/ SQM
D-01/RATE ANALYSISITEM 24.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 24.6 (Ruled/ Flush pointing on White sand stone masonry surface with lime, surkhi and marble dust mortar in the ratio of 1:1.5:1/2 {One lime : 1.5 surkhi (15% dark red and 85% light yellow surkhi) : 1/2 marble dust}. (The rate is inclusive of all materials & labours involved except scaffolding)) is derived from 5 priced inputs for 10 sqm and works out to ₹374.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 24.6DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.3.19 of SH:Marble dust mortar 1:1.5:1/2Rate as per item 3.19cum0.0232,880.6766.26
0155LABMason (average)day0.92857.00788.44
0115LABCoolieday1.37736.001,008.32
0101LABBhistiday0.93816.00758.88
9999MATSundriesL.S.4.032.279.15
BUILD-UP TO RATE
TOTAL
2,631.05
Add 1 % Water charges on “W”
+26.31
TOTAL
2,657.36
Add GST on “X” (multiplying factor 0.2127)
+565.22
TOTAL
3,222.58
Add 15% CPOH on “Y”
+483.39
TOTAL
3,705.97
Add Cess @ 1% on “Z”
+37.06
Cost of 10.00 sqm
3,743.03
Cost of 1.00 sqm
374.30
SAY
₹374.30
D-02/SOURCEPRINTED PAGE 1893
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1893

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1893. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.