Providing and applying antifungal wash treatment using 3% solution of sodium pentachlorophenate, of reputed brand and manufacturer, on cleaned sand stone surface at desired locations as per direction of Engineer-in-charge (The rate is inclusive of all materials & labours involved except scaffolding)
- Item number
- 24.4
- Analysis basis
- 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹77.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 24.4 (Providing and applying antifungal wash treatment using 3% solution of sodium pentachlorophenate, of reputed brand and manufacturer, on cleaned sand stone surface at desired locations as per direction of Engineer-in-charge (The rate is inclusive of all materials & labours involved except scaffolding)) is derived from 4 priced inputs for 10 sqm and works out to ₹77.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7775 | MAT | Sodium pentachlorophenate | Kg | 0.1 | 575.00 | 57.50 |
| 0131 | LAB | Painter | day | 0.25 | 816.00 | 204.00 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0128 | LAB | Mate | day | 0.125 | 816.00 | 102.00 |
- TOTAL
- 547.50
- Add 1 % Water charges on “W”
- +5.48
- TOTAL
- 552.98
- Add GST on “X” (multiplying factor 0.2127)
- +117.62
- TOTAL
- 670.60
- Add 15% CPOH on “Y”
- +100.59
- TOTAL
- 771.19
- Add Cess @ 1% on “Z”
- +7.71
- Cost of 10.00 sqm
- 778.90
- Cost of 1.00 sqm
- 77.89
- SAY
- ₹77.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1892
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1892. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.