Precasting and placing in position 125 mm dia Bollards 600 mm high of required shape including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollard and M.S. Pipes 40 mm dia and 450mm long with 150x150x6mm M.S. plate welded at bottom and embedded 150mm in cement concrete 1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size (Recycled Concrete Aggregate (RCA)), including necessary excavation of size 250x250x450mm deep for the same in bitumen/ concrete pavement at specified spacing

Item number
4.9A
Analysis basis
one bollard
Priced inputs
7
Derived rate
₹900.15/ ONE BOLLARD
D-01/RATE ANALYSISITEM 4.9A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.9A (Precasting and placing in position 125 mm dia Bollards 600 mm high of required shape including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollard and M.S. Pipes 40 mm dia and 450mm long with 150x150x6mm M.S. plate welded at bottom and embedded 150mm in cement concrete 1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size (Recycled Concrete Aggregate (RCA)), including necessary excavation of size 250x250x450mm deep for the same in bitumen/ concrete pavement at specified spacing) is derived from 7 priced inputs for one bollard and works out to ₹900.15 per one bollard after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4
  • 3.14/4x(0.125)x(0.125)x0.60 = 0.007 cum
  • Centering and shuttering
  • 3.14x(0.125)x0.60 = 0.24 sqm
  • M.S. pipes ( medium class)
  • 50 mm dia sleeve =1x0.30x5.10 =1.53 kg
  • 40 mm dia pipe =1x0.45x3.61 =1.62 kg
  • M.S. plate 3mm thick =(0.15x0.15)x23.55
  • =0.53 kg
  • Total =3.68 kg
  • Excavation
  • 0.25x0.25x0.45 = 0.03 cum
  • Cement concrete 1:3:6
  • 6 mm rendering (1:3) (0.24+0.01) = 0.25 sqm
ANALYSIS OF RATES · ITEM 4.9ADETAILS OF COST FOR ONE BOLLARD
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item no. 5.1.3 SH : RCCRate as per item 5.1.3Acum0.0078,404.0558.83
SUBRate as per Item no. 5.9.1 SH : RCCRate as per item 5.9.1sqm0.24392.1594.12
SUBRate as per Item no.10.1SH : Steel workRate as per item 10.1kg3.68117.35431.85
SUBRate as per Item no. 2.8.1 SH : Earth workRate as per item 2.8.1cum0.03260.307.81
SUBRate as per Item no. 4.1.5 A SH : Cement concreteRate as per item 4.1.5 Acum0.036,347.75190.43
SUBRate as per Item no. 5.23 SH : RCCRate as per item 5.23sqm0.25300.4575.11
9988MATCarriage and fixing chargesL.S.132.2729.51
BUILD-UP TO RATE
TOTAL
887.66
Add 1 % Water charges on “W-A”
+0.30
TOTAL
887.96
Add GST on “X-A” (multiplying factor 0.2127)
+6.34
TOTAL
894.30
Add 15% CPOH on “Y-A”
+5.42
TOTAL
899.72
Add Cess @ 1% on “Z-A”
+0.42
Cost for one bollard
900.14
SAY
₹900.15
D-02/SOURCEPRINTED PAGE 181
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
181

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 181. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK