CPWD Analysis of Rates · Concrete Work

Cement concrete pavement with 1:1.5:3 (1 (Reference sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate item no 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%), including 11.7) finishing complete

Item number
4.5.1A/Sub-AR-1
Analysis basis
Details of cost for one cum.
Priced inputs
5
Derived rate
8,844.45 / Cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.5.1A/Sub-AR-1 Cement concrete pavement with 1:1.5:3 (1 (Reference sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate item no 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%), including 11.7) finishing complete — is derived from 5 priced inputs for one cum and works out to ₹8,844.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:1.5:3
  • Extra labour for laying in floors etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item No.4.1.2A of SH.Concrete WorkRate as per item 4.1.2ASub-analysiscum18,127.808,127.80
0124Mason (brick layer) 2nd classMason 2nd classLabourday0.35816.00285.60
0114BeldarLabourday0.18736.00132.48
0101BhistiLabourday0.05816.0040.80
9999SundriesMaterialL.S.19.762.2744.86
TOTAL
8,631.54
Add 1 % Water charges on “W-A”
5.04
TOTAL
8,636.58
Add GST on “X-A” (multiplying factor 0.2127)
108.22
TOTAL
8,744.80
Add 15% CPOH on “Y-A”
92.55
TOTAL
8,837.35
Add Cess @ 1% on “Z-A”
7.10
Cost of 1 Cum.
8,844.45
Say
8,844.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 174. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.