CPWD Analysis of Rates · Concrete Work
Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement All works above plinth and upto floor V level
Concrete of M20 grade with minimum cement content of 270 kg /cum
- Item number
- 4.20.2.3
- Analysis basis
- Details of cost for 1.00 cum
- Priced inputs
- 13
- Derived rate
- ₹9,568.25 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.20.2.3 — Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement All works above plinth and upto floor V level Concrete of M20 grade with minimum cement content of 270 kg /cum — is derived from 13 priced inputs for 1.00 cum and works out to ₹9,568.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)
- Production cost, pumping to respective floors
- and laying in position
- Labour for pouring, consolidating & curing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0293 | Stone Aggregate (Single size) : 40 mm nominal sizeMaterial | cum | 0.65 | 1,400.00 | 910.00 |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.24 | 1,425.00 | 342.00 |
| 0982 | Coarse sand (zone III)Material | cum | 0.47 | 1,450.00 | 681.50 |
| 0367 | Ordinary/Pozzolana/Slag CementPortland Cement (OPC-43 Grade)Material | tonne | 0.27 | 5,156.00 | 1,392.12 |
| 7318 | Plasticizer / super plasticizerMaterial | gram | 1.35 | 30.00 | 40.50 |
| 0004 | Production cost of concrete by batch mix plant / ready mixed plantProduction cost of concrete by batch mix plantMachinery | cum | 1 | 450.00 | 450.00 |
| 0009 | Pumping charges of concrete including carriage for all leads and hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | 1 | 250.00 | 250.00 |
| 0155 | Mason (average)Labour | day | 0.17 | 857.00 | 145.69 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 0101 | BhistiLabour | day | 0.9 | 816.00 | 734.40 |
| 0012 | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machinery | day | 0.07 | 400.00 | 28.00 |
| 9999 | SundriesMaterial | L.S. | 13 | 2.27 | 29.51 |
| Extra cost of additional piping work and accessories etc. upto floor V level = 100% of POther | NaN | NaN | 250.00 |
- TOTAL
- 6,725.72
- Add 1 % Water charges on “W”
- 67.26
- TOTAL
- 6,792.98
- Add GST on “X” (multiplying factor 0.2127)
- 1,444.87
- TOTAL
- 8,237.85
- Add 15% CPOH on “Y”
- 1,235.68
- TOTAL
- 9,473.53
- Add Cess @ 1% on “Z”
- 94.74
- Cost per 1.00 cum
- 9,568.27
- Say
- 9,568.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 195. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.