Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing
- Item number
- 4.2.3A
- Analysis basis
- 1 cum
- Priced inputs
- 17
- Derived rate
- ₹9,671.50/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.2.3A (Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:2:4 (1 Cement : 2 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 4 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)) is derived from 17 priced inputs for 1 cum and works out to ₹9,671.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (Extra labour for lifting material upto floor V
- level = 0.75 x 2.0 = 1.50)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 0.503 | 1,425.00 | 716.78 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 0.167 | 957.00 | 159.82 |
| 0297 | MAT | Stone Aggregate (Single size) 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 0.165 | 1,400.00 | 231.00 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 0.055 | 957.00 | 52.64 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 0.334 | 1,450.00 | 484.30 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 0.111 | 957.00 | 106.23 |
| 0367 | MAT | Portland Cement (0.2225 cum)Portland Cement (OPC-43 Grade) | tonne | 0.32 | 5,156.00 | 1,649.92 |
| 0114 | LAB | Beldar | day | 0.9 | 736.00 | 662.40 |
| 0115 | LAB | Coolie | day | 0.78 | 736.00 | 574.08 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.06 | 897.00 | 53.82 |
| 0124 | LAB | Mason (brick layer) 2nd classMason 2nd class | day | 0.06 | 816.00 | 48.96 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Scaffolding | L.S. | 114.4 | 2.27 | 259.69 |
| 9999 | MAT | Sundries | L.S. | 14.3 | 2.27 | 32.46 |
| 0115 | LAB | Coolie | day | 1.5 | 736.00 | 1,104.00 |
- TOTAL
- 6,798.30
- Add 1 % Water charges on “W”
- +67.98
- TOTAL
- 6,866.28
- Add GST on “X” (multiplying factor 0.2127)
- +1,460.46
- TOTAL
- 8,326.74
- Add 15% CPOH on “Y”
- +1,249.01
- TOTAL
- 9,575.75
- Add Cess @ 1% on “Z”
- +95.76
- Cost of 1 cum.
- 9,671.51
- SAY
- ₹9,671.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 164
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 164. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.