Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing

1:1½:3 (1 cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
Item number
4.2.2
Analysis basis
1 cum
Priced inputs
14
Derived rate
₹10,357.55/ CUM
D-01/RATE ANALYSISITEM 4.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.2.2 (Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:1½:3 (1 cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 14 priced inputs for 1 cum and works out to ₹10,357.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (Extra labour for lifting material upto floor V
  • level = 0.75 x 2.0 = 1.50)
ANALYSIS OF RATES · ITEM 4.2.2DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.571,425.00812.25
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.281,400.00392.00
0982MATCoarse sand (zone III)cum0.4251,450.00616.25
0367MATPortland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)tonne0.45,156.002,062.40
0114LABBeldarday0.9736.00662.40
0115LABCoolieday0.78736.00574.08
0101LABBhistiday0.7816.00571.20
0123LABMason (brick layer) 1st classMason 1st classday0.06897.0053.82
0124LABMason (brick layer) 2nd classMason 2nd classday0.06816.0048.96
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day0.07400.0028.00
9999MATScaffoldingL.S.114.42.27259.69
9999MATSundriesL.S.14.32.2732.46
0115LABCoolieday1.5736.001,104.00
BUILD-UP TO RATE
TOTAL
7,280.51
Add 1 % Water charges on “W”
+72.81
TOTAL
7,353.32
Add GST on “X” (multiplying factor 0.2127)
+1,564.05
TOTAL
8,917.37
Add 15% CPOH on “Y”
+1,337.61
TOTAL
10,254.98
Add Cess @ 1% on “Z”
+102.55
Cost of 1 cum.
10,357.53
SAY
₹10,357.55
D-02/SOURCEPRINTED PAGE 162
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
162

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 162. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.