CPWD Analysis of Rates · Concrete Work
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing
1:1½:3 (1 cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item number
- 4.2.2
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 14
- Derived rate
- ₹10,357.55 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.2.2 — Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:1½:3 (1 cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 14 priced inputs for 1 cum and works out to ₹10,357.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (Extra labour for lifting material upto floor V
- level = 0.75 x 2.0 = 1.50)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.57 | 1,425.00 | 812.25 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.28 | 1,400.00 | 392.00 |
| 0982 | Coarse sand (zone III)Material | cum | 0.425 | 1,450.00 | 616.25 |
| 0367 | Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)Material | tonne | 0.4 | 5,156.00 | 2,062.40 |
| 0114 | BeldarLabour | day | 0.9 | 736.00 | 662.40 |
| 0115 | CoolieLabour | day | 0.78 | 736.00 | 574.08 |
| 0101 | BhistiLabour | day | 0.7 | 816.00 | 571.20 |
| 0123 | Mason (brick layer) 1st classMason 1st classLabour | day | 0.06 | 897.00 | 53.82 |
| 0124 | Mason (brick layer) 2nd classMason 2nd classLabour | day | 0.06 | 816.00 | 48.96 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachinery | day | 0.07 | 900.00 | 63.00 |
| 0012 | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machinery | day | 0.07 | 400.00 | 28.00 |
| 9999 | ScaffoldingMaterial | L.S. | 114.4 | 2.27 | 259.69 |
| 9999 | SundriesMaterial | L.S. | 14.3 | 2.27 | 32.46 |
| 0115 | CoolieLabour | day | 1.5 | 736.00 | 1,104.00 |
- TOTAL
- 7,280.51
- Add 1 % Water charges on “W”
- 72.81
- TOTAL
- 7,353.32
- Add GST on “X” (multiplying factor 0.2127)
- 1,564.05
- TOTAL
- 8,917.37
- Add 15% CPOH on “Y”
- 1,337.61
- TOTAL
- 10,254.98
- Add Cess @ 1% on “Z”
- 102.55
- Cost of 1 cum.
- 10,357.53
- Say
- 10,357.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 162. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.