Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources)
- Item number
- 4.10
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹410.85/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.10 (Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources)) is derived from 6 priced inputs for 10 sqm and works out to ₹410.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:2:4 (1 cement : 2 coarse
- sand (zone-III) : 4 graded stone aggregate 12.5
- mm nominal size)
- 10x0.040 = 0.40 cum
- 20mm size and 12.5mm size
- Add deduct for difference of cost between
- Add for delay
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.3 of SH: Concrete workRate as per item 4.1.3 | cum | 0.4 | 7,878.50 | 3,151.40 | |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | -0.67 | 1,425.00 | -954.75 |
| 0296 | MAT | Stone Aggregate (Single size) : 12.5 mm nominal size | cum | 0.67 | 1,400.00 | 938.00 |
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.4 | 897.00 | 358.80 |
| 0124 | LAB | Mason (brick layer) 2nd classMason 2nd class | day | 0.4 | 816.00 | 326.40 |
| 9999 | MAT | Sundries (Form work etc.) | L.S. | 1.95 | 2.27 | 4.43 |
- TOTAL
- 3,824.28
- Add 1 % Water charges on “W-A”
- +6.73
- TOTAL
- 3,831.01
- Add GST on “X-A” (multiplying factor 0.2127)
- +144.55
- TOTAL
- 3,975.56
- Add 15% CPOH on “Y-A”
- +123.62
- TOTAL
- 4,099.18
- Add Cess @ 1% on “Z-A”
- +9.48
- Cost for 10 sqm
- 4,108.66
- Cost for 1 sqm
- 410.87
- SAY
- ₹410.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 183
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 183. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.