CPWD Analysis of Rates · Concrete Work

Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources)

Item number
4.10
Analysis basis
Details of cost for 10 sqm
Priced inputs
6
Derived rate
410.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.10 Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources) — is derived from 6 priced inputs for 10 sqm and works out to ₹410.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:2:4 (1 cement : 2 coarse
  • sand (zone-III) : 4 graded stone aggregate 12.5
  • mm nominal size)
  • 10x0.040 = 0.40 cum
  • 20mm size and 12.5mm size
  • Add deduct for difference of cost between
  • Add for delay
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.3 of SH: Concrete workRate as per item 4.1.3Sub-analysiscum0.47,878.503,151.40
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum-0.671,425.00-954.75
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum0.671,400.00938.00
0123Mason (brick layer) 1st classMason 1st classLabourday0.4897.00358.80
0124Mason (brick layer) 2nd classMason 2nd classLabourday0.4816.00326.40
9999Sundries (Form work etc.)MaterialL.S.1.952.274.43
TOTAL
3,824.28
Add 1 % Water charges on “W-A”
6.73
TOTAL
3,831.01
Add GST on “X-A” (multiplying factor 0.2127)
144.55
TOTAL
3,975.56
Add 15% CPOH on “Y-A”
123.62
TOTAL
4,099.18
Add Cess @ 1% on “Z-A”
9.48
Cost for 10 sqm
4,108.66
Cost for 1 sqm
410.87
Say
410.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 183. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.