Skip to main content
R/DAR 2023

Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources)

Item number
4.10
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹410.85/ SQM
D-01/RATE ANALYSISITEM 4.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.10 (Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources)) is derived from 6 priced inputs for 10 sqm and works out to ₹410.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4 (1 cement : 2 coarse
  • sand (zone-III) : 4 graded stone aggregate 12.5
  • mm nominal size)
  • 10x0.040 = 0.40 cum
  • 20mm size and 12.5mm size
  • Add deduct for difference of cost between
  • Add for delay
ANALYSIS OF RATES · ITEM 4.10DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.3 of SH: Concrete workRate as per item 4.1.3cum0.47,878.503,151.40
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum-0.671,425.00-954.75
0296MATStone Aggregate (Single size) : 12.5 mm nominal sizecum0.671,400.00938.00
0123LABMason (brick layer) 1st classMason 1st classday0.4897.00358.80
0124LABMason (brick layer) 2nd classMason 2nd classday0.4816.00326.40
9999MATSundries (Form work etc.)L.S.1.952.274.43
BUILD-UP TO RATE
TOTAL
3,824.28
Add 1 % Water charges on “W-A”
+6.73
TOTAL
3,831.01
Add GST on “X-A” (multiplying factor 0.2127)
+144.55
TOTAL
3,975.56
Add 15% CPOH on “Y-A”
+123.62
TOTAL
4,099.18
Add Cess @ 1% on “Z-A”
+9.48
Cost for 10 sqm
4,108.66
Cost for 1 sqm
410.87
SAY
₹410.85
D-02/SOURCEPRINTED PAGE 183
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
183

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 183. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.