CPWD Analysis of Rates · Cladding Work
Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : Gang saw cut stone
30mm thick White sand stone
- Item number
- 8.14.5.1
- Analysis basis
- Details of cost for 1 sqm.
- Priced inputs
- 10
- Derived rate
- ₹3,256.65 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.14.5.1 — Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : Gang saw cut stone 30mm thick White sand stone — is derived from 10 priced inputs for 1 sqm and works out to ₹3,256.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 1.00 sqm + 0.05 sqm
- (Add wastage @ 5%) = 1.05 sqm
- Fixing charges
- Cement mortar 1:3 (1 cement : 3 coarse sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8684 | White sand stone gang saw cut 30 mm thickMaterial | sqm | 1.05 | 616.00 | 646.80 |
| 9999 | Extra for using white cementMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0125 | Mason (for plain stone work) 2nd classLabour | day | 0.448 | 816.00 | 365.57 |
| 0100 | BandhaniLabour | day | 0.336 | 816.00 | 274.18 |
| 0114 | BeldarLabour | day | 0.336 | 736.00 | 247.30 |
| 0115 | CoolieLabour | day | 0.336 | 736.00 | 247.30 |
| 0101 | BhistiLabour | day | 0.336 | 816.00 | 274.18 |
| 1237 | Cutting marble or sand stone slab upto 50 mm thick by mechanical deviceCutting marble or sand stone slab up to 50 mm thick by mechanical deviceMaterial | metre | 4 | 10.00 | 40.00 |
| 9999 | ScaffoldingMaterial | L.S. | 19.76 | 2.27 | 44.86 |
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.018 | 4,881.95 | 87.88 |
- TOTAL
- 2,289.16
- Add 1 % Water charges on “W”
- 22.89
- TOTAL
- 2,312.05
- Add GST on “X” (multiplying factor 0.2127)
- 491.77
- TOTAL
- 2,803.82
- Add 15% CPOH on “Y”
- 420.57
- TOTAL
- 3,224.39
- Add Cess @ 1% on “Z”
- 32.24
- Cost of 1 sqm.
- 3,256.63
- Say
- 3,256.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 412. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.