Skip to main content
W/CLIENT KEPT ANONYMOUS

Road, culverts, bridges and sea walls on an island.

The estimate for upgrading a highway on a remote island: the road, over 100 box culverts, six minor bridges, retaining walls and tetrapod armour against the sea. We produced it from the project's drawings, with the road priced at island rates and every number traced to the drawing, code or decision behind it.
Two-lane highway
47 km
Box culverts
100+
Minor bridges
6
Tetrapod sea armour
~420 m
Numbers, each sourced
~2,000
A two-lane coastal highway with a box culvert and tetrapod sea armour
THE KIND OF ROAD · TWO LANES, CULVERTS AND SEA ARMOURILLUSTRATIVE IMAGE
W-01/THE PROJECTDETAILED PROJECT REPORT · ROAD AND STRUCTURES

A 47 km road and the structures along it.

The cost estimate for a detailed project report: the bill of quantities for every piece of civil work on a highway that runs around the island, plus two short spurs. An estimator usually builds one by hand, in large spreadsheets, over about 20 working days.

The work changes along the road. Most of it is reconstruction, a long stretch is widening, the built-up areas need footpath-drains and one stretch is a new realignment. Each has its own cross-section. The schedule of where each applies splits the road into nearly 30 stretches, broken up by the bridges.

PartScale
RoadAbout 47 km of two-lane highway, in four typical cross-sections
Box culvertsOver 100, each listed with its size, plus typical drawings
Minor bridgesSix, each with its own general arrangement: PSC girders on piled foundations
WallsAbout 5 km of toe wall and about 540 m of retaining wall, 2 to 3 m high
Shore protectionAbout 420 m of precast tetrapod armour on the sea side
Roadside drainsAbout 89 km of earth drain, and footpath-cum-drain through built-up stretches
AlsoJunctions, extra widening on curves, signs, markings and safety
Typical cross-section TCS-1: a 5.5 m carriageway with 1 m hard shoulders over the existing road, with BC, DBM, WMM, GSB and 500 mm sub-grade layers, earthen drains each side, in a 14 m right of way
TCS-1 · RECONSTRUCTION OF THE EXISTING ROADPROJECT DETAILS REDACTED
TCS-125.4 kmReconstruct the existing 5.5 m road, with 1 m hard shoulders
TCS-419.0 kmWiden an existing 3.5 m road to 5.5 m
TCS-22.4 kmBuilt-up areas: 1.5 m footpath-cum-drain both sides
TCS-30.35 kmA new realignment on fresh ground
W-02/WHAT THE ISLAND DOES TO THE COSTEVERYTHING ARRIVES BY SEA

Shipping drives most of the material rates.

A mainland schedule of rates doesn’t apply here. We built up each rate from where its materials, machines and labour come from and how they are shipped across. Most of the engineering judgement in this estimate went into that.

~2.8×NO QUARRY ON THE ISLANDStone and sand come by ship from crushers on another island. Freight and handling cost nearly twice what the stone does, and aggregates are about three-quarters of the pavement cost.
12×WHERE THE EARTH COMES FROMFrom local borrow pits, sub-grade earth is about 3% of the road cost. If it has to be shipped from the mainland, its rate rises twelve-fold and it becomes about a third.
×1.3EVERY MACHINE IS SHIPPED INMachinery hire carries an island factor for sea mobilisation, standby between sailings and spares that can't be bought locally.
+45%BITUMEN IN DRUMS, FROM THE MAINLANDShipped from refinery depots. The rate in use sat about 45% above the refinery price plus freight. We flagged it. It affects about 2.5% of the road works.

The sea affects the structures as well. Exposure is severe, so the drawings call for stainless steel reinforcement throughout, and labour is priced at the territory’s own minimum wages.

W-03/THE STRUCTURESCULVERTS · BRIDGES · WALLS · SEA ARMOUR

Over 100 culverts from one schedule, and six bridges with their own drawings.

The culverts are listed in a schedule that gives each one’s size and position, and all of them are built to the same typical drawings. Each bridge has its own general arrangement drawing, and wall sizes come from a table by height. Anything the drawings don’t show was flagged rather than priced.

Minor bridge, longitudinal elevation: two 25 m spans of PSC girders on abutments and a central pier, each on pile caps over 1,200 mm cast-in-situ piles
MINOR BRIDGE · LONGITUDINAL ELEVATION · ONE OF SIXPROJECT DETAILS REDACTED
Box culvert general arrangement: sections A-A, B-B and C-C, plan with wing walls and aprons, and an apron detail
BOX CULVERT · TYPICAL GENERAL ARRANGEMENTPROJECT DETAILS REDACTED

Over 100 box culverts, each sized in the schedule and built from the typical drawing. The drawings don’t show every standard piece, such as a flexible apron or curtain walls. We flagged those against the clause that asks for them for the designer to confirm, and did not add them by default.

Tetrapod armour unit: 3D view, plan, and a table of unit sizes from 0.1 to 20 cubic metres
TETRAPOD ARMOUR UNIT · TABLE OF SIZESPROJECT DETAILS REDACTED

About 420 m of sea-side armour, built from precast concrete tetrapods. The drawing gives the unit and a table of fourteen sizes, from under a tonne to fifty, but not which size or the armour section. Those are engineering decisions, so they went to our engineer with the effect of each option.

Retaining wall: cross-section and reinforcement detail, with a dimension table by wall height
RETAINING WALL · SIZES BY HEIGHTPROJECT DETAILS REDACTED
W-04/HOW WE PRODUCED ITAI PRODUCTION · ENGINEER DECISIONS
  1. 01

    Read all the files

    Sixteen files: about 120 drawing pages, schedules, survey reports and about 100 site photos. Each page was sorted and each printed figure recorded with its position on the page.

  2. 02

    Kept only the newest drawings

    Several sets arrived in more than one issue, one reissued under a new number. Fourteen older items were recognised and set aside, each with the reason.

  3. 03

    Collected the data for each location

    For each culvert, wall and stretch, we pulled together the cross-section that applies, the road level, the schedules covering it and the site photos of what is there now.

  4. 04

    Built the quantities as live formulas

    Pavement layers, earthwork, culverts, bridges, walls, drains, shore protection, signs and junctions, each as work items under the national standard data book.

  5. 05

    Priced the road at island rates

    Two revisions, each with an abstract, a rate sheet and a list of clarifications with the cost effect of each.

  6. 06

    Sent only real decisions to an engineer

    About 60 figures needed confirming at first. That came down to 9 decisions for our engineer, such as picking the tetrapod size from a table of sizes.

R0 · RATES BUILT FROM FIRST PRINCIPLESEvery road item built up from the national standard data book, priced at island site rates: labour at the territory's minimum wages, materials at source price plus sea freight and handling, machinery with an island factor.
R1 · ON THE PROJECT'S ISLAND RATE ANALYSISThe same quantities, re-priced on the island rate analysis the project uses, with the differences explained line by line: the earth source, the bitumen price, the project size class.
W-05/EVERY NUMBER HAS A SOURCEABOUT 2,000 VALUES

Each number links back to its drawing or clause.

Each value in the estimate is stored with how it was found (read, calculated, assumed or decided), its inputs and its source. You can follow any figure from the abstract down to the highlighted spot on the drawing or the code clause, and see what moves if it changes. Two independent runs from the same files gave identical quantities, 202 of 202.

HOW EACH NUMBER CAME ABOUTSHARE OF ~2,000 VALUES
Read from a drawing: about halfCalculated by a visible formula: about halfAssumed, coded or decided: a few dozen
Documents cited: codes, manuals, published projects
41
Internal checks on every build
~160
Figures to confirm, reduced to decisions
60 → 9
Older drawing issues set aside
14
W-06/WHAT THE DRAWINGS DIDN'T SAYCLARIFICATIONS, EACH WITH ITS EFFECT

Gaps in the drawings, and how we handled them.

Drawings at this stage leave things out. Estimators often fill the gaps from experience without writing it down. Here each gap went into the estimate as a clarification, with the basis adopted and its effect on cost, so the client and designer could answer it.

  • 01Embankment heightsThe typical sections don't give the height to raise the road. Taken from the levels on the plan and profile, where it can be large.
  • 02Footpath-cum-drainAbout 4.8 km of it through built-up areas, with no detail on the sections. Held out until the standard drawing confirms it.
  • 03Existing surfaceIts thickness isn't given. Taken as 50 mm under the specifications; if thicker, it is priced as dismantling.
  • 04Sub-base gradingNot specified. Grading I adopted; the alternative is about 12% cheaper.
  • 05Culvert aprons and curtain wallsNot on the typical drawings. Flagged against the code that asks for them instead of being added to the quantities.
  • 06Breakwater sectionThe drawing gives the tetrapod unit and a table of sizes but no armour section. Raised as an engineering decision.
ABOUT THIS CASE STUDY

The client, consultant, island and roads are withheld. Drawings are cropped to the drawn views, with title blocks, stamps and chainages removed. Cost effects are shown as ratios and shares, not amounts. This describes one estimate; it is not an endorsement by the client or the consultant.

NEXT CASE STUDY · BRIDGES · SEP 2026A 150 m river bridge, estimated from one drawingRead it
ESTIMATING AND QUANTITIESHave work like this?Send the drawings or documents and your deadline, and we’ll scope it with you.Send a projectAbout the service